massingplan

A construction scheduling engine you can check by hand.

Multi-calendar CPM with all four relationship types and all ten constraint types, DCMA schedule-quality assessment, Primavera XER and MS Project interchange that keeps the logic, Monte Carlo risk, resource levelling, and baseline-to-baseline delay attribution that sums.

Standalone and self-hostable. Its engine is pure standard library, so it also drops into other products' source trees unchanged.

massingcloud.github.io/massingplan — what it does and how it is built, on one page.

pip install -e ".[dev]"
massingplan check          # boot and report the resolved config
pytest -q

Why it exists

Most scheduling tools compute sophisticated analytics on top of a network that cannot represent a real schedule, and nothing in the output says so.

The two systems this was extracted from are both examples. One has excellent Earned Schedule, Monte Carlo and delay-claim analysis running on a Finish-to-Start-only CPM core with no calendars, no lags and no constraints — and a Primavera importer that drops the relationship table, so every imported activity reports as critical with zero float. The other has a genuinely good CPM engine that works in working-day offsets, which is correct only while every activity shares one calendar, and which surfaces none of its own quality scoring in its own interface.

So the starting position here is: get the network right, prove it, and say so when you cannot.

What it does

Scheduling. Forward and backward pass on an absolute ordinal time axis with per-activity calendars. FS, SS, FF and SF with leads and lags, and an explicit choice of whose calendar the lag is measured in. All ten Primavera constraint types, split into soft (never override logic; an unmet one shows as negative float) and mandatory (do override logic, in both passes). Data date, actual dates, remaining duration as a first-class field, and the retained-logic versus progress-override switch that decides what an out-of-sequence update means.

Quality. All fourteen DCMA checks. A check with no baseline reports skipped, not passed, and is excluded from the score's denominator — the score is the percentage of runnable checks, not a number inflated by the ones that could not run. Check 12 actually runs the critical path test rather than asserting it.

Interchange. Primavera XER, Primavera P6 XML (PMXML) and MS Project MSPDI, read and write, with no third-party dependency. Including the tables that get dropped elsewhere: TASKPRED, SCHEDOPTIONS, and real calendar exceptions — a two-week shutdown that goes unparsed moves every downstream date two weeks early. P6 XML is the format that carries the series: XER exports one snapshot, so a baseline comparison out of XER needs two files and a promise about which is which, while PMXML carries the baselines in the same document as extra <Project> elements. Both XML readers refuse entity-expansion bombs, and both writers strip the C0 control characters that XML 1.0 cannot represent in any form, numeric escape included.

Risk. Monte Carlo with PERT or triangular distributions, criticality index, duration sensitivity, and percentiles that round up, because a P80 of 271.2 days is not met on day 271.

Levelling. Deterministic serial schedule generation over renewable resources, with a within float horizon that will not move the project finish and reports what it could not resolve rather than quietly extending the date.

Delay analysis. Baseline-to-baseline comparison with explicit identity matching, driving-path deltas, and attribution whose contributions sum exactly to the finish move. A residual is named PATH_SWITCH or UNEXPLAINED, never dropped to make the arithmetic work.

Forensic delay analysis, to AACE 29R-03. Three of the recommended practice's methods, each labelled with the MIP it implements rather than left as a generic "delay report":

  • MIP 3.3, observational contemporaneous — windows analysis over the update series. Critical path per window, measured against the schedule that was live at the time, so the answer does not depend on what anyone knew afterwards.
  • MIP 3.6, additive — impacted as-planned: insert the delay events into the baseline and re-run.
  • MIP 3.9, subtractive — collapsed as-built: remove them from the as-built and re-run.

The additive and subtractive models reroute only FS predecessors when an event is inserted or removed, because an SS or FF tie is not a queue and rerouting it invents logic the planner never drew. Impacts are stated in working days on a named basis calendar; where a project runs on more than one calendar that figure is approximate, and the result says so with an is_exact flag rather than quoting a tolerance — the measured error on mixed-calendar concurrency was four days, not the ±1 that reasoning suggested.

Earned Schedule. Alongside BEI, because SPI in cost units famously returns to 1.0 at completion no matter how late the project finished, and a metric that converges on "fine" is worst exactly when it is needed most.

Weather. Allowances applied against the calendar as non-working days, and removed again, so an excusable weather event and the contractor's own delay do not get counted twice on the same day. Spread evenly across the window rather than dumped at one end.

Compression. Crashing and fast-tracking evaluated as options with a cost per day recovered, ranked, and — the part that matters — re-run against the network after each choice, since crashing an activity off the critical path recovers nothing and the second-best option is frequently not the second choice.

Portfolio. Multiple projects with inter-project logic, scheduled together, plus the standalone answer for each so a planner can see what the neighbouring project is costing them.

Line of balance. Location-based scheduling with crew continuity — the thing CPM structurally cannot express. The line shift takes its maximum over every location, which is what stops a faster successor overtaking its predecessor somewhere in the middle of the building while both ends still look clear. It reports the binding location, where the buffer is fully consumed and a slip is felt first, and the continuity cost in crew-days of float given up to keep crews whole.

Takt planning. The same zones and the same take-off, planned as a train instead: every wagon occupies one zone for exactly one takt, the crew sizes move so the durations do not, and the duration is (wagons + zones − 1) × takt — readable off the plan before any of the work is estimated. What it costs is reported unrounded, per wagon: utilisation below 1.0 is capacity bought and not worked, and rounding it is how a takt plan comes to look efficient while a third of a trade stands about. A wagon that cannot meet the takt within the crews it can field is refused, not squeezed.

Last Planner. Commitments, the constraint log, and PPC — plan reliability rather than progress. Built around the fact that PPC is trivially gameable: the denominator is frozen when the week is committed, partial completion is not partial credit, an unassessed commitment makes the week unmeasurable rather than perfect, a missed commitment without a reason is refused, and constrained work cannot be committed at all. The trend is reported as a series, never as one lifetime average — five good weeks and one collapse is a project with a problem in week six, and 72% shows nothing.

The application

The engine is the point, but it ships inside a working self-hostable app: Flask and Jinja, a self-hosted SVG Gantt and line-of-balance chart with no CDN and default-src 'self' intact, SQLAlchemy persistence with Alembic migrations, organisations and four roles, API keys hashed at rest, an append-only audit log, signed outbound webhooks, optional TOTP two-factor, and optional SSO over OIDC authorization-code with PKCE.

massingplan/core/ needs none of it. It is pure standard library, held that way by an import-linter contract and a dependency-free CI job, so it can be vendored into another product's source tree and imported with no packaging change.

Design commitments

  • Hand-checkable. Every algorithm has a test network a human can verify with a pencil, and the expected values are written into the test file rather than generated by the code under test.
  • Deterministic. Same input, same answer, across runs and hash seeds. Every sort has a total-order tiebreak.
  • Nothing defaulted silently. Every coercion, drop or fallback emits an issue with a stable code and the action taken.
  • Negative float is an output. It is never clamped — not total float, not free float.
  • Core never writes. It computes and returns; the caller persists.

Verified by breaking it

A test that passes proves the test ran, not that it would notice. So the way a fix gets accepted here is: break the fix on purpose, watch a named test go red, put it back. Several claims in this repo were retracted that way rather than defended — a comment crediting a tie-break for determinism it did not provide, a weather double-count test that passed only because its three days happened to straddle Christmas, and a mixed-calendar tolerance that measurement contradicted.

The same applies to the probes. Six of them were wrong before the engine was — most memorably a run of multi-calendar probes that were single-calendar all along, because WorkCalendar(id, name, pattern, ...) takes a name second and a positional pattern lands there silently, defaulting the calendar to Mon–Fri. Where a claim has not been checked that way, it is not stated.

Status

Alpha, built in phases through P13, plus roadmap items R1–R6 (P6 XML, Earned Schedule, weather, the modelled delay methods, compression, portfolios). See SPEC.md §11 for the phase plan and ROADMAP.md for what came after it.

What is deliberately not here, so it is not discovered later: there is no mobile or offline client for Last Planner — it is a planner's board, not a foreman's phone — and no lookahead board, because storing rejected commitments beside accepted ones would put them one boolean away from the PPC denominator. SECURITY.md carries the same treatment for the security posture, including the two things that have not been done: no penetration test, and no run against a commercial identity provider.

Documentation

  • massingcloud.github.io/massingplan — the overview page, built from docs/index.html in this repo
  • SPEC.md — the research, the time-axis decision, the precedence stack, the phase plan
  • ROADMAP.md — what comes next, what it has to prove, and what is deliberately not coming
  • AGENTS.md — architecture rules, golden rules, where things live
  • CONTRIBUTING.md — what will get a pull request sent back

Licence

MIT. Portions of the engine derive from ibuilder/AIHackScheduler (MIT); the provenance is recorded in the header of each file that carries ported code.

About

Standalone construction scheduling engine: multi-calendar CPM, DCMA 14-point, Primavera XER and MS Project MSPDI, resource levelling and delay attribution. The engine is pure stdlib and vendorable.

Resources

Contributing

Security policy

Stars

1 star

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages